Ground Investigation Work Continues for the Beauly to Peterhead Overhead Line Project

SSEN Transmission is continuing to carry out permitted ground investigation activity along the proposed route for the Beauly to Peterhead 400kV overhead line, gathering crucial information to be prepared to commence full construction work, should consent be granted for the project, which will enable the connection and transportation of clean power around Great Britain.

The project, a key component of the company’s £20bn ‘Pathway to 2030’ investment programme of upgrades to the transmission network in the north of Scotland, is critical in delivering Scotland and the UK’s energy security and clean power targets.

Project teams and contractors have been carrying out walkover surveys and ground investigation works for a number of months, and continue to do so, in order to fully understand the conditions in the area, to be ready to start construction work should consent be granted.

Beauly to Peterhead is one of several onshore 400kV electricity transmission projects proposed to be delivered by SSEN Transmission. The Pathway to 2030 programme also includes existing overhead line upgrades and new 400kV substations and HVDC convertor stations across the north of Scotland – with ground investigation activity being undertaken across all projects.

Ground investigation activity for overhead lines, carried out using Permitted Development rights, typically involves the drilling of boreholes and the digging of trial pits, which allows engineers to understand the properties of the soil and rock beneath potential steel tower locations and their ability to support the structures and access tracks. Tree felling is also required in some instances, allowing safe access for ground investigation to take place, with all intrusive activity being kept to a minimum.

Kirsty McNamara, Community Liaison Manager for the Beauly to Peterhead project, said:

“Ground investigations are a necessary step in the development of any new infrastructure, and the results will help our teams and contractors to be ready to start construction on the Beauly to Peterhead project, should it get the green light.

“As our ground investigation activity continues, local community members can expect to see our teams active on the ground, and while most of the work is expected to cause very little local disruption, we would like to thank the local community for their patience while the work is carried out.

“Where slightly more intrusive assessments are needed, we will work to keep local disruption and environmental impacts to a minimum.

“As we progress through the works, the SSEN Transmission project team will continue to oversee the work being carried out by various contractors, who also employ  ecologists and archaeologists in an extra effort to ensure that work doesn’t have an impact on local wildlife or archaeological assets.”

Ground investigation activity for the Beauly to Peterhead project will continue throughout the rest of 2025 and into 2026. With the extensive public consultation period for the Beauly to Peterhead project now concluded, the project team is working on finalising its planning application, which will be submitted for consideration by Scottish Ministers later this year.

Connecting Supporting Representing